ITCertKing has a huge team of IT experts, who continue to use their knowledge and experience to study a lot of IT certification examination papers of past few years. Their findings of the research is now the product of ITCertKing, therefore ITCertKing's Microsoft 70-178 practice questions are very similar with the real exam, which can help a lot of people to realize their dreams. ITCertKing can ensure you to successfully pass the exam, and you can boldly Add ITCertKing's products to your shopping cart. With ITCertKing your dreams can be achieved immediately.
ITCertKing not only provide the products which have high quality to each candidate, but also provides a comprehensive after-sales service. If you are using our products, we will let you enjoy one year of free updates. So that you can get the latest exam information in time. We will be use the greatest efficiency to service each candidate.
On ITCertKing website you can free download part of the exam questions and answers about Microsoft certification 70-178 exam to quiz our reliability. ITCertKing's products can 100% put you onto a success away, then the pinnacle of IT is a step closer to you.
70-178 is an Microsoft certification exam, so 70-178 is the first step to set foot on the road of Microsoft certification. 70-178 certification exam become more and more fiery and more and more people participate in 70-178 exam, but passing rate of 70-178 certification exam is not very high.When you select 70-178 exam, do you want to choose an exam training courses?
Never say you can not do it. This is my advice to everyone. Even if you think that you can not pass the demanding Microsoft 70-178 exam. You can find a quick and convenient training tool to help you. ITCertKing's Microsoft 70-178 exam training materials is a very good training materials. It can help you to pass the exam successfully. And its price is very reasonable, you will benefit from it. So do not say you can't. If you do not give up, the next second is hope. Quickly grab your hope, itis in the ITCertKing's Microsoft 70-178 exam training materials.
Exam Code: 70-178
Exam Name: Microsoft (Microsoft Project 2010, Managing Projects)
One year free update, No help, Full refund!
Total Q&A: 70 Questions and Answers
Last Update: 2013-11-22
If you want to buy Microsoft 70-178 exam study guide online services, then we ITCertKing is one of the leading service provider's site. . These training products to help you pass the exam, we guarantee to refund the full purchase cost. Our website provide all the study materials and other training materials on the site and each one enjoy one year free update facilities. If these training products do not help you pass the exam, we guarantee to refund the full purchase cost.
Microsoft 70-178 is a certification exam to test IT expertise and skills. If you find a job in the IT industry, many human resource managers in the interview will reference what Microsoft related certification you have. If you have Microsoft 70-178 certification, apparently, it can improve your competitiveness.
70-178 Free Demo Download: http://www.itcertking.com/70-178_exam.html
NO.1 You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You
highlight the four tasks. Which command should you use?
A. Outdent
B. Fill Down
C. Insert Summary
D. Move Task
Answer: C
Microsoft 70-178 70-178 certification training 70-178
NO.2 You need to set the default constraint type for all new tasks to As Late As Possible. What should you
do?
A. Select all tasks, and then click Layout.
B. In the Options dialog box, enable the New Tasks are effort driven check box.
C. Select all tasks, and then set the constraint type to As Late As Possible.
D. In the Project Information window, from the Schedule From drop-down list box, select Project Finish
Date.
Answer: D
Microsoft pdf 70-178 70-178 70-178 70-178 study guide
NO.3 You manage several projects. Each project has shared resources and work distribution. You need to
ensure that you can adjust the workload for specific resources used across multiple project schedules.
What should you do?
A. Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on
each project.
B. Open the individual schedules and use the Visual Reports option. Then, use the Resource Usage view
to manually modify resource Work.
C. Open a blank project and select Insert Subproject for each project schedule. Then, use the Level
Resource function for selected resources.
D. Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
Answer: C
Microsoft certification training 70-178 exam 70-178 70-178 dumps 70-178 70-178 questions
NO.4 You manage a project that specifies all constraint types to As Soon As Possible. You discover that one
of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted
finish date on the default Gantt chart. What should you modify in the Task Information window?
A. Set the Deadline date field.
B. Set the Constraint date field.
C. Set the Finish date field.
D. Select the Mark task as milestone check box.
E. Select the Display on Timeline check box.
Answer: A
Microsoft 70-178 dumps 70-178 70-178
NO.5 You manage a project according to the schedule as shown in the exhibit.
You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
A. Create a task dependency from Task 4 to Task 6.
B. Set Task 4 as critical.
C. Add a 1 day lead to Task 4.
D. Set Task 4 as manually scheduled.
Answer: D
Microsoft 70-178 70-178
NO.6 The project you manage has only part-time resources. The part-time resources work four hours a day
from Wednesday through Saturday. You need to create a new calendar and set the calendar as the
default for your project. Which two actions should you perform? Each correct answer presents part of the
solution.
A. Select the part-time calendar from the Change Working Time window.
B. Set the calendar type to part-time for all tasks.
C. Select the part-time calendar from the Project Information window.
D. On the Project tab, Select Change Working Time, and then click Create New Calendar.
E. Change the Calendar type in the Project Options dialog box.
Answer: CD
Microsoft test 70-178 70-178 70-178 test questions
NO.7 You have a Project 2010 schedule that contains the following tasks:
Inactive tasks
Manually scheduled tasks
Manually scheduled summary tasks
Tasks that contain strikethrough font
You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are
created. What should you do.?
A. Change all inactive tasks to active tasks.
B. Change all tasks that contain strikethrough font to tasks that include normal font.
C. Change all manually scheduled summary tasks to automatic scheduling.
D. Change all manually scheduled tasks to automatic scheduling.
Answer: C
Microsoft 70-178 70-178 answers real questions 70-178
NO.8 The first major phase of your project is scheduled for a duration of 45 days. However, you do not have
task information for other phases. You need to indicate that the duration of the entire project is 200 days.
What should you do?
A. Select the Project Summary Task option.
B. Select the Summary Tasks option.
C. Create a manually scheduled summary task.
D. Update the project calendar.
Answer: C
Microsoft 70-178 70-178 test questions
NO.9 You need to view Task ID 0 on your project plan. What should you do?
A. On the Advanced tab of the Project 2010 options, select Show Status Bar.
B. On the Format tab, select Summary Tasks.
C. On the Format tab, select Project Summary Task.
D. Insert a new Summary Task.
Answer: C
Microsoft 70-178 exam dumps 70-178 test 70-178 test 70-178
NO.10 A section of your project contains only a summary task along with four subtasks and a milestone. You
discover that the section is located in the incorrect phase and has the incorrect Work Breakdown
Structure (WBS) numbering. You need to move the section to another phase of the project. You also need
to ensure that the section reflects the correct WBS numbering. What should you do?
A. Select the summary task and change the scheduling mode to Manually Scheduled.
B. Select the entire section and click Move Task.
C. Drag the summary task.
D. Modify the start and finish dates of the summary task.
Answer: C
Microsoft 70-178 test answers 70-178 test answers 70-178 70-178 certification
ITCertKing offer the latest MB7-702 exam material and high-quality 000-596 pdf questions & answers. Our 00M-663 VCE testing engine and 644-068 study guide can help you pass the real exam. High-quality 000-N45 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.
Article Link: http://www.itcertking.com/70-178_exam.html
没有评论:
发表评论